Project time Line: Project due to commence end of July and finish in August

Project Value: €75,000.00

Contractors: Bam Building Ltd

Description of Work:

Crean Mosaics have been awar

]]>
Mon, 18 Jul 2011 16:54:49 +0100 http://www.creanmosaics.com/news/latest-news/schools-out-for-summer/ Content Editor
Six week nursing home project begins http://www.creanmosaics.com/news/latest-news/six-week-nursing-home-project-begins/ Wed, 09 Mar 2011 15:41:49 +0000 http://www.creanmosaics.com/news/latest-news/six-week-nursing-home-project-begins/ Content Editor Top grades for Crean Mosaics. http://www.creanmosaics.com/news/latest-news/top-grades-for-crean-mosaics/ Wed, 09 Mar 2011 15:22:16 +0000 http://www.creanmosaics.com/news/latest-news/top-grades-for-crean-mosaics/ Content Editor Flooring Installations in progress in Trinity College Bioscience Department http://www.creanmosaics.com/news/latest-news/installation-in-progress-in-trinity-college-bioscience-department/ Wed, 09 Mar 2011 14:56:06 +0000 http://www.creanmosaics.com/news/latest-news/installation-in-progress-in-trinity-college-bioscience-department/ Content Editor Crean Mosaics work on the largest shopping centre in North Fingal http://www.creanmosaics.com/news/latest-news/crean-mosaics-work-on-the-largest-shopping-centre-in-north-fingal/ Project: Balbriggan Shopping Centre    

Project timeline: Starting Oct 2010, completion mid March 2011

Contractor: Walls Construction

Project Value:   Projected Final Account 560k 

Descrip

]]>
Wed, 09 Mar 2011 12:23:49 +0000 http://www.creanmosaics.com/news/latest-news/crean-mosaics-work-on-the-largest-shopping-centre-in-north-fingal/ Content Editor
Crean Mosaics celebrate Quality Recognition http://www.creanmosaics.com/news/latest-news/crean-mosaics-celebrate-quality-recognition/ February 2011

 

An international manufacturer and supplier of building products has awarded a top accolade for quality of service to local company Crean Mosaics, based in Charlestown.

 

The announcement was made at an event on February 16th in Portlaoise, County

]]>
Mon, 07 Mar 2011 12:12:25 +0000 http://www.creanmosaics.com/news/latest-news/crean-mosaics-celebrate-quality-recognition/ Content Editor
Crean Mosaics venture into the UK market opening Aston Crean UK Ltd http://www.creanmosaics.com/news/latest-news/crean-mosaics-venture-into-the-uk-market-opening-aston-crean-uk-ltd/ Thu, 03 Mar 2011 17:29:04 +0000 http://www.creanmosaics.com/news/latest-news/crean-mosaics-venture-into-the-uk-market-opening-aston-crean-uk-ltd/ Content Editor Flooring installation for Lidl apartment blocks http://www.creanmosaics.com/news/latest-news/flooring-installation-for-lidl-apartment-blocks/ Project: Lidl apartment blocks
Project timeline: 15 March 2010 – 9 June 2010  
Project value: £64,000.00
Contractors: P.Elliott & Company

What we did

Crean Mosaics has completed the flooring installati

]]>
Fri, 28 Jan 2011 12:32:58 +0000 http://www.creanmosaics.com/news/latest-news/flooring-installation-for-lidl-apartment-blocks/ Aisling
Aston Crean UK completes two-floor project in 3 days http://www.creanmosaics.com/news/latest-news/crean-mosaics-completes-two-floor-project-in-3-days/ Project: Pioneer Investments
Project timeline: 17 November 2010 – 20 November 2010
Contractor: Management & Construction Ltd.

What we did

Our subsidiary company Aston Crean UK worked with building contractors Management & Constructio

]]>
Fri, 28 Jan 2011 12:30:48 +0000 http://www.creanmosaics.com/news/latest-news/crean-mosaics-completes-two-floor-project-in-3-days/ Aisling
Flooring contract for Bank of India offices http://www.creanmosaics.com/news/latest-news/crean-mosaics-contracted-to-complete-bank-of-india-fit-out/ Project: Bank of India
Project timeline:  project commenced on 20 January 2011 and is expected to be complete on 4 February 2011
Project value: £15,000.00
Contractor: Management and Construction Ltd.

]]>
Fri, 28 Jan 2011 12:25:02 +0000 http://www.creanmosaics.com/news/latest-news/crean-mosaics-contracted-to-complete-bank-of-india-fit-out/ Aisling
Aston Crean UK to work on greenest hospital in the UK http://www.creanmosaics.com/news/latest-news/flooring-for-uks-greenest-hospital/ Project: Enniskillen Acute Hospital
Project value:  £2,800,000.00
Project timelines: project commenced in October 2010 and is expected to be complete in December 2011
Client: FCC Elliott

Description of work

Our sub

]]>
Fri, 28 Jan 2011 12:12:48 +0000 http://www.creanmosaics.com/news/latest-news/flooring-for-uks-greenest-hospital/ Aisling